MUMBAI, SURROUNDED WITH SEA.
One of the common problem here is the crack in the Rcc structure members like beams, columns etc.
Introduction:
STRUCTURE MEMBER REPAIR
1.0 Surface Preparation of concrete: All the spalled cracked concrete or any other pre-applied mortar shall be removed by chipping to expose the reinforcing bars. The concrete shall be chipped to a minimum depth of 10mm behind the reinforcing bars. The areas to be repaired shall be profiled to get rectangular or square shape with an inward tapering edge.
1.1 Surface preparation of reinforcement: The exposed reinforcing bars should be cleaned thoroughly to remove all traces of rust, scales, etc., by using wire brush, emery paper etc. The lateral ties/stirrups shall also be cleaned in the same way. also use air blower so that smaller dust particles can be removed. After removal of corroded portion, the diameter of the reinforcement shall be checked and compared with the drawings.
1.2 Provision of additional reinforcement: If the diameter of reinforcing bars is reduced substantially (say >20%) additional bars shall be provided as per the design. This additional reinforcement shall be properly anchored to the existing concrete by providing adequate shear connectors. Weld mesh may also be provided if found necessary.
1.3 Priming of reinforcement bars: The exposed and cleaned reinforcing bar shall be provided with a coat of Epoxy Zinc Primer such that the coated film will have a dry film thickness of 40 microns. The film shall be continuous especially in the regions where pitting, imperfections etc., are present on the surface of the bars. It is important that the rear portion of the bars should not be left without coating. A second coat if needed may
be provided to achieve a uniform and continuous film. The additional reinforcement provided and also the shear connectors shall be coated with Epoxy Zinc Primer. The weld mesh if provided shall also be coated with Epoxy Zinc Primer.
1.4 Provision of Epoxy based bonding agent: The base and hardener component of epoxy resin based bonding agent must be mixed well to get a uniform grey coloured mix. Apply the material to properly cleaned and dry concrete substrate using stiff nylon brush by scrubbing it well into the substrate. The coat should be uniform and well spread on the entire surface area of the repair patch. The mixed material must be applied before the elapse of its pot life and the new repair mortar must be applied before the elapse of overlay time. As a fully dried epoxy resin coat acts as debonding layer, the repair material should be applied whilst the bonding coat is tacky. In case the applied epoxy bond coat gets dry, an extra coat should be applied before application of repair mortar.
1.5 Applying of polymer modified concrete:
applied on top.
Thanks for looking, if any suggestion or correction please leave a comment
One of the common problem here is the crack in the Rcc structure members like beams, columns etc.
Introduction:
Concrete is a composite material that consists essentially of a binding medium, within which are embedded particles or fragments of aggregates.However in cement concrete, which is relevant to RCC structures, the binding medium is the mixture of hydraulic cement and water.
|
STRUCTURE MEMBER REPAIR
1.0 Surface Preparation of concrete: All the spalled cracked concrete or any other pre-applied mortar shall be removed by chipping to expose the reinforcing bars. The concrete shall be chipped to a minimum depth of 10mm behind the reinforcing bars. The areas to be repaired shall be profiled to get rectangular or square shape with an inward tapering edge.
1.1 Surface preparation of reinforcement: The exposed reinforcing bars should be cleaned thoroughly to remove all traces of rust, scales, etc., by using wire brush, emery paper etc. The lateral ties/stirrups shall also be cleaned in the same way. also use air blower so that smaller dust particles can be removed. After removal of corroded portion, the diameter of the reinforcement shall be checked and compared with the drawings.
1.2 Provision of additional reinforcement: If the diameter of reinforcing bars is reduced substantially (say >20%) additional bars shall be provided as per the design. This additional reinforcement shall be properly anchored to the existing concrete by providing adequate shear connectors. Weld mesh may also be provided if found necessary.
1.3 Priming of reinforcement bars: The exposed and cleaned reinforcing bar shall be provided with a coat of Epoxy Zinc Primer such that the coated film will have a dry film thickness of 40 microns. The film shall be continuous especially in the regions where pitting, imperfections etc., are present on the surface of the bars. It is important that the rear portion of the bars should not be left without coating. A second coat if needed may
be provided to achieve a uniform and continuous film. The additional reinforcement provided and also the shear connectors shall be coated with Epoxy Zinc Primer. The weld mesh if provided shall also be coated with Epoxy Zinc Primer.
1.4 Provision of Epoxy based bonding agent: The base and hardener component of epoxy resin based bonding agent must be mixed well to get a uniform grey coloured mix. Apply the material to properly cleaned and dry concrete substrate using stiff nylon brush by scrubbing it well into the substrate. The coat should be uniform and well spread on the entire surface area of the repair patch. The mixed material must be applied before the elapse of its pot life and the new repair mortar must be applied before the elapse of overlay time. As a fully dried epoxy resin coat acts as debonding layer, the repair material should be applied whilst the bonding coat is tacky. In case the applied epoxy bond coat gets dry, an extra coat should be applied before application of repair mortar.
1.5 Applying of polymer modified concrete:
- Take 1 Kg POLYALK EP( sunanda's make or equivalent), 5 kg fresh Cement, 15 Kg Quartz sand (graded).(Polymer : Cement : Quartz Sand ratio is 1:5:15). This is a globally recommended composition.
- First dry mix the cement and graded sand in a mixer
- Mix POLYALK EP with the premixed cement-sand in the mixer.
- Mixed well then apply with hand(wearing hand gloves) in layers to the surface.
- fix small aggregate stone and apply again to attain the concrete level
applied on top.
Thanks for looking, if any suggestion or correction please leave a comment
thank you.
ReplyDeleteWell, water leakage is the foremost reason of RCC damage. People neglect waterproofing during construction of the house and afterwards they regret for it.
ReplyDeleteDryshield Water Solutions Corporation
This comment has been removed by a blog administrator.
ReplyDeletePolycarbonate sheets have an excellent UV protection layer that lets in almost all of the sun’s light, while keeping away the harmful UV radiations, thus protecting the plants within.
ReplyDeletePolycarbonate Roofing Materials|Polycarbonate Roofing Sheets
Read our post on waterproofing solutions and damp proofing from the Happy Homes Blog.
ReplyDeleteInstead using epoxy zinc primer use polyalk Ep one part and one part of cement ,apply on the reinforcement and sprinkle graded slica quartz sand on it .
ReplyDeleteRead your blog its really informative to know more about waterproofing visit DRFIXIT
ReplyDeleteFantastic!Very nice information for viewer and this post surely give some useful tips to the readers. Handyman Service in Alpharetta
ReplyDeleteHandyman Service in Newnan
Thanks for sharing the best and informative article.
ReplyDeleteDubai Waterproofing Contractors
Great information you have shared here, through this post. Thanks and keep sharing such valuable updates through your side.
ReplyDeleteDubai Waterproofing Contractors
That looks pretty rough, thanks for sharing this!
ReplyDeleteElcometer
Very informative and It was an awesome post. I love reading your fantastic content. Are you searching for a Terrace waterproofing in Mohali? Our expert team is highly trained professionals with 10 year experience. Our aim is to provide the best and reliable service for your home or office. Contact us today!
ReplyDeleteThis comment has been removed by the author.
ReplyDelete